== 2011 2-3 July ==
== 2011 2-3 July ==


FB: still working on the code, most of it compiles but still many issues.
FB: still working on the code, most of it compiles but still many issues, need to make the error() functions from CHAMP and CHARA compatible, as well as the char_waiting() function.
CHAMP now cooled, pressure is high ~1.5e-6 but lots of outgassing from the inner dewar so will see when stabilized.

Revision as of 20:02, 4 July 2011

2011 1 July

FB: mainly worked on integrating CHAMP with chara system, which requires solving some dependencies and conflicts. This is not an easy task as a lot of the code has been duplicated into files specific to CHAMP. Vacuum pumped CHAMP in prevision for the run, pressure ~5e-6.

2011 2-3 July

FB: still working on the code, most of it compiles but still many issues, need to make the error() functions from CHAMP and CHARA compatible, as well as the char_waiting() function. CHAMP now cooled, pressure is high ~1.5e-6 but lots of outgassing from the inner dewar so will see when stabilized.