Did the alignment on beams 4, 5, 6 so as not to impede on CLIMB run (+ we need to measure the fringe position again now that the IR5 repeatability problem has been cleared).  
Did the alignment on beams 4, 5, 6 so as not to impede on CLIMB run (+ we need to measure the fringe position again now that the IR5 repeatability problem has been cleared).  


All computers had to be rebooted due to a long power outage this night, including lothlorien, wolverine, zoot. Had to restart all servers (shutters, etc.).
All computers had to be rebooted due to a long power outage this night, including lothlorien, wolverine, zoot. Had to restart all servers (shutters, etc.). Green laser is completely disaligned, need to restart crtscrut again to launch server to use pico to realign it...

Revision as of 00:57, 25 April 2011

Daily Log:

2011 April 24:

Xiao filled the dewar before FB arrived, and pressure seems high (3e-6). After refilling both dewars, the pressure went down to 6e-7.

Did the alignment on beams 4, 5, 6 so as not to impede on CLIMB run (+ we need to measure the fringe position again now that the IR5 repeatability problem has been cleared).

All computers had to be rebooted due to a long power outage this night, including lothlorien, wolverine, zoot. Had to restart all servers (shutters, etc.). Green laser is completely disaligned, need to restart crtscrut again to launch server to use pico to realign it...