  1. from scratch alignment of champ. preparation for picomotor tests at night.
  1. from scratch alignment of champ. preparation for picomotor tests at night.
  2. need to order new cable for ealing mounts (db9->rj45)
  2. need to order new cable for ealing mounts (db9->rj45)
  3.  
  3. measured asymmetry in picomotor motions for dicroics [not for tower of power yet]
4. ordered ealing cable for champ dicroic
5. got 100x100 readout working for champ
6. tested baseline button for mirc -- worked in lab but seemed to fail on sky
7. fringes with mirc!


-----
-----

Revision as of 09:48, 4 August 2010

See last set of notes from Engineering 2010May-June


Daily Log:

2010 August 3:

1. from scratch alignment of champ. preparation for picomotor tests at night.
2. need to order new cable for ealing mounts (db9->rj45)
3. measured asymmetry in picomotor motions for dicroics [not for tower of power yet]
4. ordered ealing cable for champ dicroic 
5. got 100x100 readout working for champ
6. tested baseline button for mirc -- worked in lab but seemed to fail on sky
7. fringes with mirc!

Ettore Pedretti came out for 2 weeks to work on upgrade xenomai on mirc/champ

How thing were left


Xiao Che came for 3 weeks to lead the MIRC observing and do some small MIRC improvements

work finished and needs to be done


Fabien Baron came for 4+ weeks to observe with CLIMB/CLASSIC and to work on CHAMP engineering

Stefan Kraus came out for 2+ weeks to help with CHAMP


Rafael Millan-Gabet came up for XX nights to help with CHAMP engineering


JDM came out for 3 weeks to help with champ commissioning (4 telescope operation!)